ST. TAMMANY PARISH — Louisiana DOTD posted apparent bid results Wednesday, November 18, for the final LA 3241 connection between the I-12/LA 434 interchange and LA 36, with Denley Brown Contractors, LLC ranked first after construction price and proposed contract time were combined.

Denley Brown submitted a construction bid of $71,110,474.90 and proposed a contract time of 600 days. DOTD's table adds a $6.3 million time-cost component, producing a total evaluated bid of $77,410,474.90.

Barriere Construction Co., LLC submitted the lowest construction-only price, $70,937,699.92, but proposed 725 days. Its $7,612,500 time-cost component brought its evaluated total to $78,550,199.92, placing it second. The time component is calculated at $10,500 per day in DOTD's table; the evaluated total should not be confused with the construction-only price.

Five bidders are listed for project H.004957.6. The other evaluated totals are $85,225,877.83 for Huey P. Stockstill, LLC; $94,216,249.56 for JB James Construction LLC; and $113,453,804.06 for RNGD Construction LLC. DOTD lists an estimated construction cost of $97,362,364.20.

These are apparent results, not a confirmed contract award. DOTD states that the bids remain subject to correction, verification and validation. A proposed contract time does not establish a construction start or opening date.

The work includes clearing, grading, drainage, paving, bridge construction and lighting. The connection is Segment 1, the final portion of the LA 3241 corridor between I-12 near Lacombe and Bush, according to DOTD's June 11, 2025 project update.

That update announced the opening of Segment 2, an eight-mile section between LA 435 near Talisheek and LA 36. Combined with the previously opened Segment 3 between Bush and Talisheek, the agency said more than 13 miles of the corridor were open.

Completing the southern connection would link that corridor to Interstate 12. DOTD has described the overall project as intended to improve mobility and connections for communities in St. Tammany and Washington parishes.

Sources: Louisiana DOTD's November 18, 2026 apparent bid results, Notice to Contractors, and June 11, 2025 LA 3241 project update.

Source

Louisiana Department of Transportation and Development